AC HIGH PRESSURE SWITCH REPLACEMENT - Continued
INSTALLATION
PLSAC050
NOTE
Lightly lubricate preformed packing with PAG oil prior to installation.
Ensure preformed packing is in place in high pressure switch prior to installation.
1. Install preformed packing (6) and high pressure switch (5) on hose 2521 (7). Torque high pressure
switch (5) to 7.5-10 ft-lbs. (10-14 Nm).
NOTE
Install cable ties as required.
2. Connect connector (3) to connector (4).
3. Connect connector (1) to connector (2).
FOLLOW-ON MAINTENANCE
1. Connect batteries (TM 9-2320-364-20).
2. Install left side noise panel and rubber flap (WP 0051).
3. Perform leak test inspection (WP 0052).
END OF WORK PACKAGE