4120-01-238-4277">

 

Click here to make tpub.com your Home Page

Page Title: INSTALL COMPRESSOR
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 

TM 5-4120-393-14
5-28. Compressor (B1) (cont)
12. Fill reservoir with fluorocarbon refrigerant, R-1 1, and start the pump. Continue filling the reservoir with refrigerant,
R-11, until it begins to pour out of the return line. Continue flushing for at least 15 minutes.
13. Reverse the pump connections, replace the filter with a new filtering medium, and backflush t e system for an
h
additional 15 minutes.
14. Remove the pump, reservoir and filter and dehydrator jumper.  Place an empty container below the compressor
connections, and connect a cylinder of dry nitrogen to each dehydrator connection in turn. Blow down each leg of the
2
system at 50 psig (3.5 kg/cm ) for at least 30 seconds.
INSTALL COMPRESSOR
CAUTION
The compressor is supplied with a complete charge of oil. Take care that oil is not
lost when handling and installing compressor.
NOTE
If any refrigeration piping was disconnected with the compressor being replaced,
transfer the piping to the replacement compressor before installing it in the air
conditioner. Check to see that replacement compressor is equipped with the same
type of heaters as were on the old compressor. If not, remove heaters and related
parts from old compressor or replace with new ones.  Locate parts and mount
using old compressor as a guide. Installation of the thermostat mounting angle
will require drilling of two holes. Match drill from angle.
1.
Lift compressor through the lower front panel opening and position it on base pan.
2.
Lift or tilt compressor and install washer and flat washer between each of the four compressor mounting feet and the
base pan.
3.
Install a flat washer and a washer on each of the four bolts, then install the bolts beneath the pan base and install nuts
on bolt.
4.
Wrap wet rags around compressor at connection points and while brazing direct flame away from compressor.
5.
While purging the system with nitrogen, braze the tubing joints. See para 5-10 and 5-11.
6.
Replace dehydrator. See para 5-16.
7.
Connect electrical connector plug (P11) to connector (J11) on compressor terminal box.
8.
Leak test all newly connected joints and those in the repair area. See para 5-12.
9.
Reinstall and tape in place tubing insulation that was removed from suction line tubing. If it was damaged, replace
with tubing insulation.
10. Connect electrical connection plug P2 to connector J2 on condenser fan motor.
11. Evacuate and charge the refrigerant system. See para 5-13 and 5-14.