WARNING
To prevent injury to personnel and damage to the equipment, make sure generator set is
not operating when connecting or disconnecting power cable from terminal box. Refer to
WP 0006 00 for generator set shutdown instructions.
1. Electrical power required to operate the refrigeration unit can be supplied by the generator set or an external power
source. Conversion of the refrigeration unit from one power source to the other is accomplished by changing power
cable connections.
2. A five-foot long cable is supplied with the refrigerated container to connect to the generator set or external power.
3. The five foot power cable is wired into the Generator Set terminal post and the other end is connected to the
Refrigeration Unit power cable connector.
GENERATOR SET PREPARATION.
1. Remove two bolts (1, Figure 1) from refrigerated container frame generator set slides (2).
2. Using two men, release the retention latches (3) simultaneously and pull from both sides on the generator set, lifting
rings (4) until generator set unit slides uniformly out.
NOTE
Steps 3 through 4 are not necessary after the auxiliary fuel line assembly MWO has been applied.
3. Open door (5) and remove the fuel line (6) from the storage compartment (7).
4. Remove cap (8) from fitting (9) on generator set (10) and cap (11) from fuel tank elbow (12). Store cap (11) in storage
compartment (7) and close door (5).
5. Connect auxiliary fuel line (6) to auxiliary fuel tank elbow (12) and to fitting (9) on generator set (10).
|