4-16. CONTROL PANEL COVER, DOOR HOLDER CLIPS, AND BARREL BOLTS REPLACEMENT.
This task covers: a. Removal b. Installation
INITIAL SETUP
Materials/Parts:
Equipment Conditions:
Lock Washers (6 each barrel bolt assembly)
Control panel cover door raised and latched.
1, Appendix G
Lock Washers (5)
3, Appendix G
Rivets (4 each identification plate)
4, Appendix G
Rivet (1 each door holder clip)
5, Appendix G
a.
Control Panel Cover Replacement.
(1) Removal. Remove five bolts (1), lock washers (2), flat washers (3), and control panel cover (4). Discard lock
washers.
(2) Installation.
(a) Remove two bolts (5), lock washers (6), and barrel bolt clip (7) from old cover (4). Repeat for second
barrel bolt clip. Discard lock washers.
(b) Install barrel bolt clip (7), two new lock washers (6), and bolts (5). Repeat for second barrel bolt clip.
(c) Drill out four rivets (8) and identification plate (9) from old cover (4). If the rivets cannot be removed,
notify direct support maintenance to remove them.
(d) Install identification plate (9) and four new rivets (8). If the rivets cannot be installed, notify direct support
maintenance to install them.
(e) Drill out four rivets (10) and warranty plate (11) from old cover (4). If the rivets cannot be removed, notify
direct support maintenance to remove them.
(f)
Install warranty plate (11) and four new rivets (10). If the rivets cannot be installed, notify direct support
maintenance to install them.
4-43
|