TM 9-4110-257-14
4-25. TIME DELAY RELAYS TD1 AND TD2 TESTING AND REPLACEMENT.
This task covers: a. Testing b. Removal c. Installation
INITIAL SETUP
Materials/Parts:
Equipment Conditions:
Adhesive Tape
Refrigeration unit shut down (para 2-7) and
Figure F-35, Appendix F
battery
disconnected (para 4-35).
Marker tags (4)
Control panel cover door raised and latched.
7, Appendix E
Lock Washers (2)
1, Appendix G
Lock Washers (4)
6, Appendix G
a.
Testing. (See Figure 1-4.)
(1) Be sure battery has been disconnected and remove two bolts (1) and lock washers (2). Open control panel
(3). Discard lock washers.
Figure 4-19. Time Delay Relay
4-63
|