TM 9-4120-367-14
TM 07592B-14/1
Location/Item
Cheok Power
Supply
- Continued
Action
Power supply circuit breaker must be
OFF. Installation must be checked prior
to turning ON power.
b.
a.
b.
a.
b.
c.
d.
e.
f.
Connect mating power supply connector to J1 or
J11.
Check installation.
Perform steps in paragraph 3.6 before placing
unit in operation.
Remove power at Main Circuit Breaker.
Disconnect power cable at air conditioner.
Remove insulating material from area around air
conditioner.
Connect sling to lifting handles (4).
Position hoist (wrecker) next to shelter in order to
lift air conditioner.
Connect sling to two handles (one either side) on
condenser section.
The maintenance personnel MUST be
visible to hoist or wrecker operator and in
a position to guide air conditioner away
from shelter.
Remarks
Unit ready for operation
Checkout. Paragraph 3.6.
High voltage can kill.
Air conditioner weighs
256 pounds (116.1 kg).
3-17
3.5 INSTALLATION OR REMOVAL. - Continued
Installation
Check
R e m o v al
|