TM 9-4120-389-14
c. Removing packaging. Remove the cushioning around the top of the cabinet and retain, if reuse is
anticipated. Remove the preservation barrier by tearing around the bottom of the cabinet. Remove the
technical publications envelope and accessory sack that are taped to the cabinet and put them in a safe place.
WARNING
DO NOT LIFT without holding unit in upright position. Otherwise, unit will fall
over and will cause injury to personnel.
NOTE
It is recommended that cabinet be left bolted to shipping pallet until time to
place it in installation position. All receiving inspection actions can be
conducted without removal from pallet.
d. Remove pallet. Raise the cabinet and remove the four carriage bolt assemblies that hold the tiedown
bars to the pallet from the underside of the pallet. Remove the four bolts that hold the two tiedown bars to the
unit base. Remove and retain the pallet and carriage bolt assemblies and the tiedown bars and bolts, if reuse
is anticipated. Be sure to remove all remaining barrier material from the underside of the cabinet base. Lower
the cabinet to the floor in the desired position and remove the sling and hoist.
4-4. RECEIVING INSPECTION
Perform receiving inspection of the air conditioner in the following manner:
a. Inspect the equipment for damage incurred during shipment. If the equipment has been damaged, report
damage on DD Form 6, Packaging Improvement Report.
b. Check the equipment against the packing slip to see if the shipment is complete. Report all discrepancies
in accordance with the instruction of DA PAM 738-750.
c. Check to see whether the equipment has been modified.
4-4
|