TM 5-4120-361-14
(ii) Refer to figure 4-10 and
install the junction box.
(6) Condenser Fan Motor High Speed
Relay.
(a) Testing.
Check for loose
connections and cracked or broken cas-
ing.
Check for continuity with a multi-
meter.
If no continuity exists or if
the casing is cracked or broken, replace
the relay.
(b) Removal.
(i) Refer to figure 4-10 and
remove the junction box.
(ii) Refer to figure 4-16 and
remove the condenser high speed relay.
(c) Installation.
install
install
Relay.
connect
(i) Refer to figure 4-16 and
the condenser high speed relay.
(ii) Refer to figure 4-10 and
the junction box.
(7) Condenser Fan Motor Low Speed
(a) Testing.
Check for loose
ions and cracked or broken cas-
ing.
Check for continuity with a multi-
meter.
If no continuity exists, or if
the casing is cracked or broken, replace
the relay.
(b) Removal.
(i) Refer to figure 4-10 and
remove the junction box.
(ii) Refer to figure 4-16 and
remove the condenser low speed relay.
(c) Installation.
(i) Refer to figure 4-16 and
install the condenser low speed relay.
(ii) Refer to figure 4-10 and
install the junction box.
(8) Compressor Relay.
(a) Testing.
Check for loose
connections and cracked or broken cas-
ing.
Check for continuity with a multi-
meter.
If no continuity exists or if
the casing is cracked or broken, replace
the relay.
(b) Removal.
(i)
Refer to figure 4-10 and
remove the junction box.
(ii) Refer to figure 4-16 and
remove the compressor relay.
(c) Installation.
(i) Refer to figure 4-16 and
install the compressor relay.
(ii) Refer to figure 4-10 and
install the junction box.
(9) Terminal Boards.
(a) Testing.
Check for loose
connections, loose mounting or cracked
or broken casing; replace if defective.
(b) Removal.
(i) Refer to figure 4-10 and
remove the junction box.
(ii) Refer to figure 4-16 and
remove the terminal boards.
(c) Installation.
(i) Refer to figure 4-16 and
install the terminal boards.
(ii) Refer to figure 4-10 and
install the junction box.
4-28.
Transformer and Resistor.
a.
Removal.
(1) Refer to figure 4-10 and re-
move the junction box.
(2) Refer to figure 4-17 and re-
move the transformer and resistor.
Re-
move resistor from transformer if either
is faulty when tested as follows:
b.
Testing.
(1) Refer to wiring diagram (fig-
ure 1-5) and use a multimeter to test
the transformer for continuity through
both the primary winding and the secon-
dary winding.
If no continuity exists
through either winding, replace the
transformer.
4-26
|