4-10. GENERAL.
To insure that the air conditioner is ready for operation at all times it must be inspected
systematically so that the defects may be discovered and corrected before the result is
serious damage or failure. Defects discovered during operation of the unit shall be noted
for future corrections to be made as an operation has ceased. Stop operation which would
damage the equipment if operation were to continue. All deficiencies and shortcomings
shall be recorded together with the corrective action taken on DA Form 2404 Equipment
Inspection and Maintenance Inspection Worksheet, at the earliest opportunity. If your
equipment fails to operate, troubleshoot with proper equipment. Report any deficiencies
using proper forms. See DA PAM 738-750.
4-11. PREVENTIVE MAINTENANCE CHECKS AND SERVICES (PMCS) TABLE.
Dry cleaning solvent (Item 16, App. D) used to clean parts is potentially
dangerous to personnel and property. Avoid repeated and prolonged skin
contact. Do not use near open flame or excessive heat. Flash point of
solvent is lOOoF (38oC).
Do not use compressed air for cleaning purposes except where reduced to less
than 30 psi (2.1 kg/cm2) and then only with effective chip guarding and
personal protective equipment.
Interval Columns. The columns headed "W" and "Q contain a dot (o) opposite the
appropriate check. If a given check is performed weekly, a dot is shown opposite the
check in the "W" column; if the check is accomplished quarterly, the dot is shown in the
column headed "Q".
|