TM 9-4110-257-14
4-37.
PUSH SWITCHES S9 AND S10 TESTING AND REPLACEMENT. - Continued
Figure 4-31. Push Switches
NOTE
Sleeving insulation covers only terminal C on one side of push switch, but
must cover both terminals NO and NC on the other side.
(6)
Slip sleeving insulation (1) over exposed terminals and shrink in place using heat gun.
b.
Removal.
(1)
Remove sleeving insulation (1).
(2)
Tag and disconnect wire leads (2).
(3)
Remove two self locking nuts (4), flat washers (5), bolts (6), and push switch (3). Discard self
locking nuts.
4-94
|