This task covers:
Inspection
INITIAL SETUP:
Tools
Tool kit, service, refrigeration unit (Item 1, Appendix B)
Personnel: 1
Material:
Brazing alloy, silver, QQ-B-654, Grade III (Item 21, Appendix E)
Equipment Conditions:
WARNING
Disconnect input power to the air conditioner before performing any internal maintenance. Voltages
used can KILL. Shutting the unit off at the control panel does not disconnect unit power.
1.
Disconnect air conditioner input power at source.
2.
Swing open control box assembly (para 4-45).
INSPECTION
1.
Check for signs of leakage (see Figure 5-32). Leak test if leak is suspected (para 5-15).
2.
If a leak is detected at distributor joint, braze joint (para 5-14).
3.
If a capillary line leak is detected, contact General Support Maintenance.
FOLLOW ON PROCEDURE
1.
Close control box (para 4-45).
2.
Connect air conditioner input power at source.
Figure 5-32. Distributor