Remove tags.
5
Carefully form and position capillary tubing. Coil excess capillary tubing in three loops located
at clamp attachment point.
6
While purging the system with nitrogen, braze the capillary end into the tube tee. See WP0071
and WP0072.
7
Using screwdriver, secure the capillary loops with a screw and clamp and three equally spaced
tiedown straps.
8
Replace the dehydrator. (See WP0080).
9
Leak test all newly connected joints and those in the repair area. (See WP0073).
10
11
Install top condenser cover. (See WP0044).
12
Connect power.
TESTING
Press and release reset button on switch. Use a continuity tester or multimeter to check for continuity
between terminals 1 and 2 on switch. If there is continuity, the switch is properly closed. If no
continuity is found, press and release reset button again. If there is still no continuity, switch must be
replaced.
END OF TASK