TM 5-4120-386-14
TRANSFORMER-INSPECT/TEST/REPLACE.
This task covers:
a.
Inspect
Replacement
d.
b.
Removal
Installation
e.
Test
c.
INITIAL SETUP
Equipment
Condition
Para
Condition Description
Evaporator Inlet Louver removed.
Front top cover removed.
Control Module removed.
Junction Box partially removed.
Test Equipment
Variable Voltage Power Source (AC/DC)
Materials/Parts
Special Tools
Solder (Item 2, App. D)
Tool Kit SC 5180-90-CL-N18
Flux (Item 15, App. D)
Heat Gun
LOCATION/ITEM
ACTION
REMARKS
Inspect
Inspect transformer for external
damage.
Removal
Disconnect air conditioner power
source before doing work on elec-
trical system.
a.
Remove screws (10) and lock-
washers (11).
b. Remove shrink sleeving from
two input and six output
terminals.
c.. Tag and desolder wires
connected to input and output
terminals.
d. Lift transformer (9) out of
unit.
4-70
|