TM 9-4120-430-14
0014 00
Table 1. Service Upon Receipt Checklist
ITEM
ACTION
REFERENCE
LOCATION
1. Exterior
Louvers, Covers, Drains, Guards,
Perform operator PMCS before you
Controls, Switches
operate.
2. Front
Main Power Connectors
a. Inspect connectors for damage.
b. Replace damaged connector.
CHECKING UNPACKED EQUIPMENT
1. Inspect the equipment for damage incurred during shipment. If the equipment has been damaged, report the damage
on DA Form 368 Quality Deficiency Report (QDR).
2. Check the equipment against the packing slip to see if the shipment is correct and complete. Report all discrepancies
in accordance with the instructions of DA PAM 738-8
3. Check to see whether the equipment has been modified.
INSTALLATION
General
1. Air conditioner is assembled and ready for operation.
2. It contains full charge of refrigerant and compressor oil.
Mounting
1. Place the unit on a firm, level surface to permit proper drainage of water that condenses out of the air or rain.
2. Position the unit so that the control panel, the condenser, and the evaporator louvers are accessible to the operator
and to maintenance personnel.
3. Check that there are no obstructions in front of any air intake or discharge louvers or other openings.
4. Refer to Figure 1. The dimensions for base-mounting holes on the enclosure mount (6) are shown on the dimension
and hardware location illustration. The resilient mount (3), washer (2), spacer (4), elastomeric tube (5), and cap
screw (1) are shipped with the air conditioner. Refer to Figure 2 showing front, top, and rear views for installation
dimensions.
5. Connect a drain line if necessary.