CAUTION
Protect the wires from the torch during de-soldering and re-soldering.
Failure to comply may result in damage to equipment.
5. Solder the inlet and outlet connections. After the valve body cools, assemble the diaphragm and
valve plunger. Attach the compressor terminal box. Attach the wires that were removed from the
back of the control panel.
6. Pressurize the system with dry nitrogen and check for leaks as outlined in WP 0031 00.
7. If no leaks are found, reinstall the solenoid coil:
a. Gently push the coil onto the stem until it snaps into place.
b. Reinstall the electrical plug with the four screws.
8. Evacuate the low side and perform the low side pump up procedure in accordance with WP 0031 00.
9. Complete the refrigerator operation check in accordance with WP 0010 00 (item 7).
Solenoid Coil
1. Gently push the coil onto the stem until it snaps into place.
2. Reinstall the electrical plug with the four screws.
3. Leak check, evacuate, and charge the system IAW WP 0031 00.
4.
Complete the refrigerator operation check in accordance with WP 0010 00 (item 7).
END OF WORK PACKAGE