TM 10-8145-222-23
0022
ADJUST CONTINUED
NOTE
If refrigerant charge is not sufficient, it will have to be serviced to complete this task.
Refrigeration servicing can be found in WP 0014.
7. Tighten compressor pressure regulating valve jam nut (Figure 1, Item 2) against set screw (Figure 1, Item 3)
with 8mm hex wrench.
8. Verify pressure (26 1 psig) by reading low side of manifold gauge.
9. Shut down refrigeration unit (TM 10-8415-222-10, Operating Procedures).
10. Close discharge and suction service valves.
11. Replace cap (Figure 1, Item 1) on compressor pressure regulating valve.
12. Remove manifold gauge set (WP 0014, Service).
13. Install top-middle panel (WP 0013, Install).
14. Install top-left panel (WP 0013, Install).
15. Place MTRCS back into normal operation (TM 10-8415-222-10, Operating Procedures).
END OF TASK
END OF WORK PACKAGE
0022-3/4 blank