TM5-4120-383-14
Section III
MAINTENANCE PROCEDURES
GENERAL.
The procedures in this section have been arranged in the order in
which the items appear in the direct (F) maintenance level column
on the Maintenance Allocation Chart (MAC) which is provided in
Step-by-step procedures have been provided for all
action authorized to be performed by direct maintenance in the
order in which they appear on the MAC. Actions authorized to be
performed by organizational and general support maintenance have
been duly noted; step-by-step procedures for these actions may be
found in Chapters 4 and 6 respectively.
FABRIC COVER.
For removal, inspection, lubrication, cleaning and installation see
a. Repair. Minor rips, cuts, tears, or punctures may be
repaired by applying a patch to the inside surface.
b. Replace.
For damage of greater extent, or missing eyelets
or snap fasteners replace the entire cover.
TOP COVERS.
For removal, cleaning, inspection and installation see paragraph
4-11.
a. Repair.
The only authorized repairs for these panels are
replacement of gaskets, insulation and information plates.
(1) Use only gaskets, insulation, or name plates identified
in TM5-4120-383-24P.
NOTE
An initial supply of adhesive is supplied as Item 2,
Section II, Expendable Supplies and Materials List.
(See Appendix E.)
(2) Remove as much old gasket or insulation material as
possible by pulling or scraping it away from the metal surface.
|