TM5-4120-383-14
5-32.
COMPRESSOR.-Continued
(5) Swing four access covers into place and tighten screws.
(6) Braze tube connections in accordance with paragraph 5-13.
(7) Replace dehydrator.
(Not necessary if replaced after
refrigerant system cleaning and purging.)
(8) Connect P10 connector.
(9) Leak test newly connected joints and all connections in
the area.
(10) Install top rear cover (para 4-11).
(11) Evacuate and charge the refrigeration system in
accordance with paragraphs 5-15 and 5-16.
TUBING AND FITTINGS.
The refrigeration system contains a number of pieces of copper
tubing in a variety of material grades, sizes, lengths, and shapes,
and a number of elbows, tees and adapters in several sizes.
Observe the following when replacing any piece of tubing or fitting
in the system:
Be sure the refrigeration system is fully discharged
and purged, and that dry nitrogen is flowing through
the system at a rate of 1-2 cfm (0.028 - 0.057
3
m /minute) before brazing or debrazing.
Test/Replace.
a. Replace tubing and fittings only with equal material, grade,
size, length, and shape as the item removed.
b.
Leak test the entire refrigeration system in accordance with
c. Replace the dehydrator and leak test the dehydrator flare
fittings as the final step in any maintenance action that required
the refrigeration pressure system to be opened.
Evacuate and charge the refrigeration system in accordance
d.
with paragraphs 5-15 and 5-16 after all other maintenance actions
are completed.
5-83/(5-84 blank)
|