TM 9-4120-425-14&P
OPERATION UNDER USUAL CONDITIONS
INITIAL SETUP:
Maintenance Level
Operator
References
WP 0011-00 (PMCS)
Equipment Condition
Mode selector switch in OFF position.
Correct voltage and phase power source (208 volts, three phase, 50/60hz) available.
Perform operator PMCS (WP 0011-00) as necessary.
General Installation Site Requirements
A relatively level surface.
An unobstructed flow of air from outside the area.
An unobstructed flow of air from inside the conditioned area.
An unobstructed flow of air from outside the conditioned area to the fresh air intake.
STARTING AND OPERATING INSTRUCTIONS FOR COOLING
Starting
1.
Perform the preventive maintenance checks and services before operation.
2.
Check for correct voltage and phase at power source (208 volts, three phase, 50/60 hz).
3.
Roll up and tie the canvas cover.
4.
Ground the unit.
5.
Connect the main power to the unit.