REPLACE CONTINUED
WARNING
Lifting or moving heavy equipment incorrectly can cause serious injury. The
evaporator weighs 120 pounds and is bulky to work with. Never attempt to move
more than 42 pounds alone. Use a minimum of four people. Three people holding the
unit, while one aligns piping on the evaporator with piping on the container, performs
soldering tasks, and installs evaporator mounting hardware.
NOTE
Step 5 is for compartment 2 (aft) evaporator only. If installing compartment 1
(forward) evaporator, omit step 5 and proceed to step 6. If installing compartment 2
(aft) evaporator, omit step 6.
5. Install evaporator guard (Figure 8, Item 7) and two spacers (Figure 8, Item 6) on evaporator (Figure 8, Item 4)
and carefully lift evaporator into position inside container.
6. Carefully lift evaporator (Figure 8, Item 4) into position inside container.
7. Align three refrigerant pipes on evaporator with three pre-mounted couplings of corresponding mating
refrigerant pipes on container and carefully slide evaporator piping into couplings.
8. Install six evaporator (Figure 8, Item 4) mount bolts (Figure 8, Item 1), washers (Figure 8, Item 2), and new lock
washers (Figure 8, Item 3) and tighten until lock washers compress.
NOTE
Step 9 is for compartment 2 (aft) evaporator only. If installing compartment 1
(forward) evaporator, omit step 9 and proceed to step 10.
9. Install aft evaporator air deflector (Figure 8, Item 9) to evaporator (Figure 8, Item 4) and secure using seven