( 3 ) R e p l a c e . R e p l a c e the transformer if damaged to the extent that
serviceability would be impaired or if any failure occurs during testing. Refer to
steps (4) and (5) for removal of defective transformer and the installation of a new
transformer.
( 4 ) Removal.
(See figure 3-18.)
(5) Installation.
( a ) R e f e r t o f i g u r e 3 - 1 8 a n d install transformer in the junction box.
( b ) I n s t a l l j u n c t i o n b o x p a n e l and lower access panel.
m.
Terminal Boards TB1 and TB2
WARNING
Disconnect the air conditioner from the
e l e c t r i c a l power source before attempt-
ing to perform the following procedures
on the terminal boards.
(1)
Inspection.
( a ) Turn selector switch to "OFF'" position and disconnect the air
from electrical power source.
conditioner
( b ) L o o s e n a t t a c h i n g screws and r e m o v e lower access panel.
( c ) R e m o v e a t t a c h i n g screws and washers and remove, junction box
cover.
( d ) I n s p e c t t e r m i n a l boards TB1 and TB2 for damage which would im-
pair
serviceability.
( 2 ) R e p l a c e . R e p l a c e terminal board T B 1 and/or TB2 if there is any
d a m a g e which would impair serviceability. Refer to steps (3) and (4) for removal and
installation of terminal boards.
(3) Removal.
( a ) R e f e r t o f i g u r e 3 - 1 2 a n d remove junction box from unit.
( b ) R e f e r t o f i g u r e 3 - 1 5 a n d remove bracket from junction box.
(c)
Refer
t o f i g u r e 3 - 1 9 and remove terminal board TB1 and/or TB2
f r o m junction box.
(4) Installation.
( a ) R e f e r t o f i g u r e 3 - 1 9 a n d 3 - 1 5 a n d i n s t a l l t e r m i n a l board TB1
a n d / o r TB2 and bra&et in junction box.
( b ) I n s t a l l l o w e r a c c e s s p a n e l and secure with attaching screws.
|