Click here to make tpub.com your Home Page

Page Title: Section III: OPERATING UNDER USUAL CONDITIONS
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 

TM 5-4120-369-14
OPERATING UNDER USUAL CONDITIONS
Section III.
GENERAL.
a. The instructions in this section are published for the information and guidance of the
personnel responsible for the operation of the air conditioner.
The operator must know how to perform every operation of which the air conditioner is
b.
capable.  This section gives instructions on starting and stopping the air conditioner, and detailed
operating instructions.  Since nearly every condition presents a different problem, the operator
may have to vary the given procedure to fit the condition.
UNLOADING EQUIPMENT.
The total weight of the air conditioner is 290 pounds (132 kg.). Use a hand truck or fork-
lift of at least 500 pounds capacity to unload the unit.  Keep unit upright during the unloading
operation.
UNPACKING EQUIPMENT.
Move the unit as near to the site of installation as possible.  Remove crating hardware and
metal straps being careful not to damage the unit with the tools used for uncrating.
INSPECTING AND SERVICING EQUIPMENT.
a. Inspection. Inspect the entire air conditioner for signs of damage, missing or loose
hardware, an any defects that may have been incurred during shipment.  Report all damage and
defects to organizational maintenance.
b. Servicing. Perform the daily preventative maintenance services listed in paragraph
2-4. Be sure all hardware is securely in place.
INSTALLATION.
General.  The air conditioner is shipped assembled and ready for operation. It contains
a.
a full charge of refrigerant and compressor oil.  Install the unit on a firm, level surface to allow
proper condensate drainage.  Place it so that the control panel and condenser and evaporator
louvers are accessible to the operator and to maintenance personnel. Be sure there are no
obstructions in front of any air intake or discharge louvers or other openings that may cause
insufficient flow of air in to or out of the air conditioner.  If the unit is van mounted, report
any such obstructions to organizational maintenance.
b. Lifting. Check for broken or deformed lifting ring attachment and hardware before
lifting air conditioner.  Lift with crane or forklift truck.
Use lifting harness with 4-leg spreader bar. Each leg must
be capable of withstanding a concentrated load of more than
500 pounds.  If spreader bar cannot be used, the angle bet-
ween the harness legs and the top of the air conditioner must
not be less than 45-degrees.
c. Mounting. Base mounting hole dimensions are shown on figure 2-3. The resilient mount
parts shown in figure 2-4 are shipped with the air conditioner.
For safe operation connect a No. 10 AWG (min.) ground
wire between the air conditioner ground connection and
an earth ground, as shown in figure 2-5.

Privacy Statement - Press Release - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business