6. Install lanyard chain (Figure 2, Item 6) and secure to pin (Figure 2, Item 2) using one screw (Figure 2, Item 7)
and washer (Figure 2, Item 9).
7. Install lanyard chain (Figure 2, Item 6) and secure to PLS roller (Figure 2, Item 8) using one screw (Figure 2,
Item 3), new lock washer (Figure 2, Item 4), and washer (Figure 2, Item 5).
8. Install pin (Figure 2, Item 2) into PLS roller (Figure 2, Item 8) and secure using locking clip (Figure 2, Item 1).
9. Install PLS roller in either stored or deployed position it was removed from (TM 10-8415-222-10, Install).
Replace Swing Out Panels Lanyard, Clips
1. Unload insulated container to extent necessary to gain access to damaged swing out panel (TM 10-8415-222-
10, Unloading).
2. Remove four bolts (Figure 3, Item 5) and lock washers (Figure 3, Item 9) securing applicable mount bracket
(Figure 3, Item 6) and swing out panel (Figure 3, Item 3) to container. Discard lock washers.
3. Remove swing out panel (Figure 3, Item 3) and place on a flat work surface.
WARNING
Wear eye protection when drilling old rivets out. Rivet chips can be hot and fly in
various directions.
4. Drill out and remove rivet (Figure 3, Item 1, or Item 7) securing lanyard (Figure 3, Item 2) or clip (Figure 3,
Item 8) to swing out panel (Figure 3, Item 3).
5. Remove lanyard (Figure 3, Item 2) or clip (Figure 3, Item 8).
6. Install new lanyard (Figure 3, Item 2) or clip (Figure 3, Item 8) to swing out panel (Figure 3, Item 3) and secure
using rivet (Figure 3, Item 1, or Item 7).
NOTE
The pin is a key-chain style connector. No tools are needed to install the pin to the
lanyard.
7. Install new pin (Figure 3, Item 4) onto lanyard (Figure 3, Item 2).
8. Install swing out panel (Figure 3, Item 3) and mounting bracket (Figure 3, Item 6) to container and secure using
four bolts (Figure 3, Item 5) and new lock washers (Figure 3, Item 9).
9. Reload any removed cargo into container (TM 10-8415-222-10, Loading).