TM 10-8145-222-23
0067
REPLACE CONTINUED
11. Remove cap screw securing back of receiver.
12. Remove 3/8-inch check valve (Figure 1, Item 4) and 1/4-inch check valve (Figure 1, Item 6) from receiver
(Figure 1, Item 9). Discard both check valves.
13. Install new 3/8-inch check valve (Figure 1, Item 4) and new 1/4-inch check valve (Figure 1, Item 6) into receiver.
14. Secure back of receiver with cap screw.
NOTE
Before tightening the receiver mounting hardware, make sure that the refrigeration
lines are properly aligned.
15. Install receiver (Figure 1, Item 9) onto bottom panel assembly and secure with one nut (Figure 1, Item 7) and
washer (Figure 1, Item 8).
16. Connect hot gas line (Figure 1, Item 5) to receiver 1/4-inch check valve (Figure 1, Item 6).
17. Connect condenser line (Figure 1, Item 3) to receiver 3/8-inch check valve (Figure 1, Item 4).
18. Connect piping (Figure 1, Item 1) to receiver outlet valve (Figure 1, Item 2).
19. Perform refrigerant leak check (WP 0014, Service).
20. Perform evacuation and dehydration (WP 0014, Service).
21. Charge system with refrigerant (WP 0014, Service).
22. Install top-left panel (WP 0013, Install).
23. Install left-side panel (WP 0013, Install).
24. Install front panel assembly (WP 0013, Install).
25. Reconnect battery (WP 0053, Reconnect).
26. Operate refrigeration unit to verify refrigeration cycles are operational after receiver replacement (TM 10-8415-
222-10, Operating Procedures).
27. Place MTRCS back into desired mode of operation (TM 10-8415-222-10, Operating Procedures).