TM 10-8145-222-23
MAINTAINER MAINTENANCE
DIESEL ENGINE GLOW PLUGS
TEST, REPLACE
INITIAL SETUP:
Tools and Special Tools
References
TM 10-8415-222-10
General Mechanic Tool Kit (WP 0096, Table 2, Item 5)
Personnel Required
Quartermaster and Chemical Equipment Repairer
TM 10-8145-222-23P
Equipment Condition
Refrigeration unit shut down (TM 10-8415-222-10)
TEST
WARNING
The exhaust system will become extremely hot after a short period of operating time.
Allow engine to cool for 30-minutes before performing maintenance.
1. Open control panel access door (Figure 1, Item 1).
2. Place POWER ON/DOWN switch (Figure 1, Item 2) on control panel to DOWN position.
WARNING
Falling from the top of the MTRCS can result in serious injury or death to personnel.
Whenever performing maintenance on top of the MTRCS, always maintain three
points of contact to aid in stability. Never attempt to walk backwards while on top of
the container.
3. Access top of MTRCS using roof access provided.
Figure 1. POWER ON/DOWN Switch.